Planner and Project Plans 1, 3 and 5: Which Licence Matches How You Run Projects

10 min read Updated October 5, 2026 Microsoft Licensing Guides

Fix it now

Microsoft has renamed these plans: they are Planner Plan 1, Planner and Project Plan 3 and Planner and Project Plan 5. Basic task and plan management is already included with Microsoft 365. Plan 3 is the level at which the Project desktop application appears, on up to five PCs per user. Project for the web retired in August 2025 and Project Online retires on 30 September 2026.

  1. Use what you already have first. Microsoft 365 includes basic plans: tasks, My Tasks, My Day and Grid, Board, Schedule and Chart views.
  2. Buy Planner Plan 1 when teams need premium plans with Timeline, People and Goals views but nobody needs a desktop scheduler.
  3. Buy Planner and Project Plan 3 when you need the Project desktop application, baselines, critical path, advanced dependencies with lead and lag, and sprints.
  4. Ask for the current Plan 5 feature list in writing before paying the difference over Plan 3. Microsoft’s published Planner comparison no longer distinguishes them on capability.
  5. Do not buy either plan for Project Online. It stopped being sold on 1 October 2025 and retires on 30 September 2026.
  6. Consider perpetual Project Standard 2024 or Professional 2024 for a lone scheduler with nothing to share.

If nobody needs a desktop scheduler, stop here: the included Planner capability or Plan 1 covers it. Below is what actually changed, what each tier does, and how to price the Plan 5 question honestly.

Why it happens

Two things have changed since most comparisons of these plans were written, and both affect what you should buy.

First, the names. Microsoft’s own Planner plans page now lists Planner included with Microsoft 365, Planner Plan 1, Planner and Project Plan 3 and Planner and Project Plan 5. If a quote says ‘Project Plan 3’, it means Planner and Project Plan 3; ask for the current product name so you can check what you are being sold.

Second, the browser side moved and one product is going away. Microsoft retired Project for the web in August 2025 and redirected its users to Planner for the web. Project Online stopped being sold on 1 October 2025 and retires on 30 September 2026, with full support until that date. The Project desktop client and Project Server on premises continue and are available to both existing and new customers.

The requirement is task tracking, not scheduling

You have this one if Work is a list of things with owners and dates, viewed as a board or a grid, and nobody has ever asked what happens to the finish date if one task slips.

  1. Start with what Microsoft 365 already includes at no extra cost: creating and editing tasks and plans, My Tasks across everything assigned to you, My Day, and Grid, Board, Schedule and Chart views.
  2. Move to Planner Plan 1 only when that falls short. Plan 1 unlocks premium plans and adds the Timeline, People and Goals views.
  3. Forcing a marketing team, a software team or an operations team onto a desktop scheduler produces expensive schedules nobody maintains.

Somebody genuinely builds schedules

You have this one if Several hundred tasks, nested summary levels, lag on dependencies, a resource calendar that closes for a fortnight in August, and a client or auditor who wants variance explained against a baseline.

  1. Planner and Project Plan 3 is the tier where the Project desktop application appears, installable on up to five PCs per user.
  2. It is also where baselines and critical path, advanced dependencies with lead and lag, task history, the assignments view, sprints, custom fields and report creation appear.
  3. Buy it for the people who build and maintain schedules, and nothing more for the people who only read them. That is the most common overspend in this product family.

You are being quoted Plan 5 for portfolio management

You have this one if A quote assumes Plan 5 for demand management, portfolio selection, resource capacity modelling or timesheets.

  1. Those capabilities historically lived in Project Online, which retires on 30 September 2026, so a purchase made on that basis may not deliver what the quote describes.
  2. Microsoft’s current published Planner comparison describes Plan 3 and Plan 5 as offering advanced capabilities with premium plans, and does not set out a feature list that separates them.
  3. So do not accept a feature claim you cannot check. Ask the supplier for Microsoft’s current, dated Plan 5 feature list, confirm each capability you are buying against it, and price the difference per seat per year over the number of seats that would actually use it.

Full reference

The tiers under their current names

Capability Included with Microsoft 365 Planner Plan 1 Planner and Project Plan 3 / Plan 5
Create and edit tasks and plans Yes Yes Yes
My Tasks and My Day Yes Yes Yes
Grid, Board, Schedule and Chart views Yes Yes Yes
Premium plans No Yes Yes
Timeline (Gantt), People and Goals views No Yes Yes
Sub-tasks, premium plan templates No Yes Yes
Backlogs and sprints No Yes Yes
Milestones and project goals No Yes Yes
Project desktop application No No Yes, up to five PCs per user
Baselines and critical path No No Yes
Advanced dependencies with lead and lag No No Yes
Task history and assignments view No No Yes
Report creation and custom fields No No Yes
Project Manager agent No No Yes, with a separate Copilot licence

Microsoft’s published comparison does not currently separate Planner and Project Plan 5 from Plan 3 on capability. Treat the two as one column until a supplier shows you a current Microsoft feature list that distinguishes them, and price the difference against the specific capabilities that list names.

What retired, and what did not

  • Project for the web: retired in August 2025. Users were redirected to Planner for the web, and premium plans are reached in the unified Planner experience.
  • Project Online: end of sale on 1 October 2025, full support until its retirement on 30 September 2026.
  • Project desktop: continues, and is available to existing and new customers.
  • Project Server on premises: continues, and is available to existing and new customers.
  • Project 2016 and Project 2019: out of support since 14 October 2025.

If you are still running Project Online, the retirement date is the planning event, not the licence. Get the data out and decide where the portfolio and resource process will live before the date rather than after it, because a licence purchase made now will not extend that deadline.

When the desktop application is genuinely the requirement

Nothing in a browser grid handles a plan with several hundred sequenced tasks, nested summaries, lag on dependencies and a resource calendar with exceptions, and no amount of board-based tooling replaces constraint-based scheduling. The cases where the desktop scheduler earns its licence are recognisable: construction, engineering and manufacturing programmes with hard dependencies and contractual milestones; any work where a baseline must be shown and variance explained to a client, funder or auditor; plans with resource contention where the same specialist is committed to three streams; and migration or rollout programmes with hundreds of small tasks across many sites.

Everywhere else, the honest answer is that the included Planner capability or Plan 1 covers what people actually call project management, and buying a scheduler produces documents rather than delivery.

The perpetual desktop editions

Project is still sold as a one-time purchase, as Project Standard 2024 and Project Professional 2024, and in the Office LTSC 2024 volume-licensed family. Both install the desktop scheduler on a single PC and never expire, with security fixes for a fixed support window ending 10 October 2029 and no cloud service. For a lone planner who builds schedules, prints them and mails them as files, the perpetual Professional edition does the job for one payment. The moment two people need to share a resource pool or publish plans for others to update, only the subscription plans work, and the subscription also gives five PCs per user rather than one.

Which to buy, by situation

  • Team leads tracking assigned work with dates: start with the Planner capability already in your Microsoft 365 subscription and move to Planner Plan 1 only if it falls short.
  • A team that wants Gantt views, sprints and goals but no desktop scheduler: Planner Plan 1.
  • One or two professional project managers building real schedules: Planner and Project Plan 3 for them, Plan 1 or nothing for the people who only read the plan.
  • A PMO with cross-project reporting: Plan 3 for the managers, and get the current Plan 5 feature list in writing before adding Plan 5 seats.
  • An organisation still on Project Online: plan the exit before 30 September 2026, and do not buy licences expecting the retirement to move.
  • A single scheduler on a fixed desk with nothing to share: perpetual Project Professional 2024, bought once.

When a licence is the actual fix

If you need the installed Project desktop application, baselines, critical path and advanced dependencies, Planner and Project Plan 3 is the tier that provides them, and the browser-only plans cannot be extended to reach it. Arco supplies Planner Plan 1, Planner and Project Plan 3 and Planner and Project Plan 5 alongside the perpetual Project Standard 2024 and Professional 2024 editions. Tell us how many people build schedules and how many only need to read them, and we will price a mix rather than putting the whole team on one tier. If somebody has quoted you Plan 5, ask us to check it: Microsoft’s current published comparison does not separate Plan 5 from Plan 3 on features, and the portfolio capability those quotes usually describe lived in Project Online, which retires on 30 September 2026. If your requirement stops at task tracking, we will point you at what your Microsoft 365 subscription already covers instead.

Questions people ask about this

Why do the plan names look different from my last quote?

Microsoft renamed them. The current names on Microsoft’s Planner plans page are Planner Plan 1, Planner and Project Plan 3 and Planner and Project Plan 5, alongside the Planner capability included with Microsoft 365. A quote saying ‘Project Plan 3’ means Planner and Project Plan 3; ask for the current name so you can check the feature list against Microsoft’s page.

Is Project Online still available?

No, not to buy. Microsoft ended sales of Project Online on 1 October 2025 and will retire it on 30 September 2026, with full support until that date. Project for the web retired in August 2025 and its users were moved to Planner for the web. The Project desktop client and Project Server on premises continue for existing and new customers.

Do I need Plan 3 for everyone who looks at a project plan?

No, and this is the most common overspend. Only the people who build and maintain schedules need the Project desktop application. Readers and task updaters sit on Planner Plan 1 or on the Planner capability already included with their Microsoft 365 subscription, which covers tasks, plans, My Tasks, My Day and the Grid, Board, Schedule and Chart views.

What does Plan 5 add over Plan 3?

Microsoft’s current published Planner comparison describes both as offering advanced capabilities with premium plans and does not set out a feature list that separates them. The portfolio selection, demand management and timesheet capabilities that older comparisons attribute to Plan 5 lived in Project Online, which retires on 30 September 2026. Ask your supplier for Microsoft’s current, dated Plan 5 feature list, confirm each capability you are buying against it, and multiply the per-seat difference by the seats that would genuinely use it before agreeing.

Is there a free way to do basic project tracking?

Yes. Microsoft includes basic plans with eligible Microsoft 365 subscriptions – Business Basic, Business Standard, Office 365 E1, E3 and E5 among them – covering task and plan creation and editing, My Tasks, My Day and the Grid, Board, Schedule and Chart views. It will not do critical path scheduling or baselines, but for a large share of what gets called project management it is sufficient.

Was this article helpful?

Your feedback helps us improve our documentation.

Related articles

Review Entra ID P1 vs P2: Conditional Access or Full Identity Governance? Review E3 Plus Add-Ons or Straight to E5? Building the Cheaper Security Stack Review Downgrade Rights Explained: Running Older Windows on a New Licence Review SQL Server Web vs Standard: Web Edition Ends at SQL Server 2022
โ† Back to Knowledge Base